Hi Experts,
We have a requirement to schedule a job so that it runs every 15 mins on specified days of the month. We have scheduled it as below
The Management Console Guide only mentions the below
"For the Data Services scheduler, enter the time (hours, minutes,and either AM or PM) for the scheduler to repeatedly run the job for the selected duration (in minutes) at the selected interval (in minutes)."
Since the job needs to run for 11 days we have entered the value in 'Duration (minutes)' field as 60*24*11=15840. Is this the correct value to be entered or the guidance needs to be interpreted differently? Another reason we want to be sure about this is the job is currently executing till 17th of each month rather than stopping on the 6th. I'm aware of certain other SAP notes on this issue like Note 1250124 but just want to confirm the above parameter value.