We are getting ready for an upgrade to BODS 4.2. On our test box we have installed IPS 4.1SP07 with BODS 4.2 SP05ll in , all on a Linux box. We have gotten to the point of setting up schedules and I was wondering if anyone has come across the issue of setting up dependencies....
Ex.
Job1 runs
upon completion kicks of
Job2 Job3 Job4
when all those jobs are complete
Job5 should kick off
With the removal of the Event Server from the IPS has anyone found a way to schedule the dependencies like this?